Preparation for PED Trauma Bay Construction

  • Pediatric Trauma Bay construction, which is scheduled to begin Monday, February 16 with a completion date of early June. We will update the team with any timeline changes.

  • Biggest changes you should be aware of:

    • G147-150 are closed.

      • Remaining items will be removed in the coming weeks by BioMed.

    • An additional pediatric code cart will be placed in the flex area 

    • G146 is the new resuscitation room

    • G131-135 are outfitted for use, with peds bedside carts, wall suction, etc.

    • G145 will be the new “ortho room” if possible.

      • Our ortho teammates are aware, but also willing to complete ortho sedations in any room as needed.

    • Central monitoring is live and active in the PED for G130-135.

    • G130 is storing beds currently.

    • Ortho cart, suture cart, US machine, EKG machine have been relocated to the clean utility room (by soiled utility).